* All items shall be accompanied by a Certificate of Conformity [C.O.C] indicating that all the materials, processes, and finished products supplied under the purchase order comply with applicable specifications/drawings.
A Certificate of Conformity must contain all identifying items of the supplied product [Order Nr. Item description, No. Specification / Drafting and Edition, Quantity, Serial No. If required.
The supplier shall execute FAI before the commencement of serial production for the first time or two or more years after the last serial production. The contents of the FAI shall be agreed upon in writing between the quality manager and the supplier quality manager.
* The quality assurance manager should be informed when the FAI is completed and await its guidance. If all requirements are met, the vendor will submit the FAI report along with the delivery of the first production series. According to the ISO 9001:2015 standard, an FAI is required whenever a change in location, design, method, or production processes occurs or two years have elapsed from the previous production.
* The supplier will not change the production process, which will cause deviation from the drawing/specification tutorials.
* If the supplier wishes to make any change in the process, he must contact the quality manager in writing, accompanied by a detailed explanation, and follow his instructions.
* A vendor who wishes to obtain an exception certificate from the product features will submit a written request on the MRB form; the application will
Be discussed by the customer [if required].
* If a discrepancy is found regarding the quality or compliance with the delivery dates, the customer will be sent a complaint report.
* It is the responsibility of the supplier to investigate the discrepancy and to submit a report to the Quality Manager that will include proof of root cause analysis and corrective action, including a date for completion of the activities and a date for the effectiveness test.
* The report will be forwarded to Eilor within 14 working days at the latest.
* The supplier will monitor an inappropriate product discovered in its facilities
* The supplier and manufacturer shall supply each item in a manner consistent with the documents.
* The materials purchased will be accompanied by a certificate of analysis [C.O.A] of the manufacturer, with traceability between the production amount on the material and the actual dose on the packaging and the MSDS report.
* If not otherwise specified, all active components supplied to the Company shall have a production code not exceeding 24 months from the delivery date and passive components for a period of 5 years. The customer’s approval must be obtained if a deviation exceeds the production date above.
* All items with a limited life span shall be valid for at least six months from the delivery date.
To reduce the risk of providing materials or counterfeit goods, the following requirements must be met:
* The supplier shall ensure that items are packaged not to damage the end of the conveyance, production, and storage.
* The parts shall be packed in such a way as to prevent corrosion and mechanical damage.
*The following details shall be recorded on each package:
* As part of the packaging process, the supplier will ensure that no foreign objects are found inside the packaging.
*Rubber items according to specifications shall be packed according to MIL-B-131 TYP1 2; each bag shall be thermally sealed and shall bear a sticker bearing the following details: item description, item number, number of items in the bag, expiration date, date of manufacture, Production order.
* The supplier shall make available to Eilor representatives all the necessary means of testing to prove compliance.
* This order is subject to inspection or inspection by Eilor on the supplier’s website before shipment.
* The vendor will notify the QA / QC Manager at least three working days ahead of schedule.
* The supplier must inform EILOR of the production date to coordinate the control dates.
* A certificate of analysis of the raw material from the original manufacturer complying with the drawing/ordering requirements; the documentation should include S dose, analysis report, and traceability to purchase order/drawing.
* Packaging and transportation of raw materials must be in a manner that will ensure 100% prevention of damage/scratches in the raw material.
* Raw material will be supplied from only one melting pot.
* Goods that do not meet the order’s requirements and have been notified to the supplier are his responsibility to collect them for further handling.
* If the supplier has not collected the goods within 48 hours of receiving the notification, the goods will be delivered to the supplier using a forwarder. They will be binding on the supplier at full payment.
*Materials and processes must comply with the ROHS standard.
*The process manufacturer’s quality reports and raw materials/reference materials must contain a declaration of ROHS compliance
* Upon receipt of the order and the contract survey, the supplier must ensure that the production documents are complete and valid, meet the quality requirements attached to the order, and examine the unique processes and requirements in the documentation accompanying the order.
* The contractor is responsible for identifying the type of coating according to the applicable standards, the difficulty of the material defined in the drawing, special requirements that appear in the drawing, and the documentation received in the order.