• Certificate of conformity to requirements:
* All items shall be accompanied by a Certificate of Conformity [C.O.C] indicating that all the materials, processes, and finished products supplied under the purchase order complies with applicable specifications/drawings.
A Certificate of Conformity must contain all identifying items of the supplied product [Order Nr. Item description, No. Specification / Drafting and Edition, Quantity, Serial No. If required.
• Marking:
* The supplier will not make any change in the production process that will cause deviation from the drawing/specification tutorials.
* If the supplier wishes to make any change in the process, he must contact the quality manager in writing, accompanied by a detailed explanation, and follow his instructions.
* A vendor who wishes to obtain an exception certificate from the product features will submit a written request on the MRB form; the application will be
• Corrective action:
* If a discrepancy is found regarding the quality or compliance with the delivery dates, the customer will be sent a complaint report.
* It is the responsibility of the supplier to investigate the discrepancy and to submit a report to the Quality Manager that will include proof of root cause analysis and corrective action, including a date for completion of the activities and a date for the effectiveness test.
* The report will be forwarded to Eilor within 14 working days at the latest.
* The supplier will monitor an inappropriate product discovered in its facilities
• Catalog items and off-the-shelf products:
* Each item shall be supplied by the supplier and manufacturer, with consistency between the documents.
* The materials purchased will be accompanied by a certificate of analysis [C.O.A] of the manufacturer, with traceability between the production amount on the material and the actual dose on the packaging and the MSDS report.
* If not otherwise specified, all active components supplied to the Company shall have a production code not exceeding 24 months from the delivery date and passive components for a period of 5 years. The customer’s approval must be obtained if there is a deviation beyond the production date above.
* All items with a limited life span shall be valid for at least six months from the delivery date.
• Auditing – F.A.I:
* For aviation customers, the process will be carried out in accordance with AS9102 customer requirements. FAI testing shall be carried out before the supply of the first-generation units. To prove compliance with the requirements of the order and the applicable specifications, the continued production of the unit units without FAI approval shall be the exclusive responsibility of the supplier.
* the supplier shall execute FAI before the commencement of serial production for the first time or with two or more years passed since the last serial production. The contents of the FAI shall be agreed upon between the Quality Manager and the Supplier Quality Manager in writing.
* The quality assurance manager should be informed when the FAI is completed and await its guidance. If all requirements are met, the vendor will submit the FAI report together with the delivery of the first production series. In accordance with the requirements of the AS9102 standard, an FAI is required whenever a change in location, design, method, or production processes occurs, or two years have elapsed from the previous production.
• Marking:
* The supplier will not make any change in the production process that will cause deviation from the drawing/specification tutorials.
* If the supplier wishes to make any change in the process, he must contact the quality manager in writing, accompanied by a detailed explanation, and follow his instructions.
* A vendor who wishes to obtain an exception certificate from the product features will submit a written request on the MRB form; the application will be discussed by the customer [if required].
• Corrective action:
* If a discrepancy is found regarding the quality or compliance with the delivery dates, the customer will be sent a complaint report.
* It is the responsibility of the supplier to investigate the discrepancy and to submit a report to the Quality Manager that will include proof of root cause analysis and corrective action, including a date for completion of the activities and a date for the effectiveness test.
* The report will be forwarded to Eilor within 14 working days at the latest.
* The supplier will monitor an inappropriate product discovered in its facilities
• Catalog items and off-the-shelf products:
* Each item shall be supplied by the supplier and manufacturer, with consistency between the documents.
* The materials purchased will be accompanied by a certificate of analysis [C.O.A] of the manufacturer, with traceability between the production amount on the material and the actual dose on the packaging and the MSDS report.
* If not otherwise specified, all active components supplied to the Company shall have a production code not exceeding 24 months from the delivery date and passive components for a period of 5 years. The customer’s approval must be obtained if there is a deviation beyond the production date above.
* All items with a limited life span shall be valid for at least six months from the delivery date.
• Avoiding and reducing purchases of counterfeit items:
To reduce the risk of providing materials or counterfeit goods, the following requirements must be met:
• Packing:
* The supplier shall ensure that items are packaged so as not to damage the end of the conveyance, production, and storage.
* The parts shall be packed in such a way as to prevent corrosion and mechanical damage.
*The following details shall be recorded on each package:
* As part of the packaging process, the supplier will ensure that no foreign objects are found inside the packaging.
*Rubber items according to specifications shall be packed according to MIL-B-131 TYP1 2; each bag shall be thermally sealed and shall bear a sticker bearing the following details: item description, item number, number of items in the bag, expiration date, date of manufacture, Production order.
• Anti-fungal resistance:
In the case of rubber items, the supplier shall attach the confirmation of compliance with the test for resistance to fungi according to MIL-STD-810 METHOD 508.1
• Anti-fungal resistance:
* Goods that do not meet the order’s requirements and have been notified to the supplier, it is his responsibility to collect it for further handling.
* If the supplier has not collected the goods within 48 hours of the receipt of the notification, the goods will be delivered to the supplier using a forwarder and will be binding on the supplier at full payment.
• ROHS compliance [when required in order/drawings]:
*Materials and processes must comply with the ROHS standard.
*The process manufacturer’s quality reports and raw materials/reference materials must contain a declaration of ROHS compliance
• Contract survey:
* Upon receipt of the order and the contract survey, the supplier must ensure that the production documents are complete and valid, meet the quality requirements attached to the order, and examine the unique processes and requirements in the documentation accompanying the order.
* The contractor is responsible for identifying the type of coating according to the applicable standards, the difficulty of the material defined in the drawing, and special requirements that appear in the drawing and the documentation received in the order.